A year ago Norrfield’s engineers spent three weeks on each grid connection study. Now a study takes a morning, and every one is checked twice before an engineer signs it.
Norrfield was our first customer outside contracts and finance. Grid studies are long, numerical and unforgiving, which made them a good test of the second route.
What went well
Two hundred and twelve studies ran in the first year. Nineteen were sent to an engineer because the two solvers disagreed, and every one of those had a real modelling error.
What we changed
The review screen now shows both solver results side by side.
Studies can be rerun from any step, not only from the start.
Engineers sign inside the trail, so the signature travels with the study.